Case study

The project: foul waste treatment plant.

Location: Cheshire.

Client: elderly care group. .

The contract involved installation of a 48,000 litre waste processing tank manufactured by Klargester together with all necessary drainage runs and access controls.

The processing unit was seated on, and secured to, an underground concrete base and then encased in concrete.

Logo - SLE Construction, Cheshire.

 

Sheet piles ready for driving into ground as side support for main excavation.

 

Excavation complete - ready for waste processing tank.

 

Initial filling of the waste processing vessel prior to encasing in concrete.

Temporary steel piles removed and access ports concreted in position.

Greens Environmental tanker.